Interconnection & Net Energy Metering

Notice of Net Energy Metering (NEM) Program Closure

The Net Energy Metering (NEM) Program has reached its cap and is closed, effective January 1, 2018. See the Net Energy Metering (NEM) Program Closure section below for more information.

Before You Get Started

Effective January 1, 2017, BVES, Inc. will no longer allow customers to install their solar systems directly to a sub-panel, due to safety concerns and EUSERC requirements. See EUSERC Drawing 502 for compliance requirements.

The information in our Net Energy Metering (NEM) / "Customer Solar" Section will be helpful in answering most of your questions about Net Energy Metering and customer generation. This section has information for Residential & Small Commercial customers (30 kW or less), and Large Commercial customers (30 kW or more but no more than 1,000 kW).

What You Need To Apply

Please complete the forms included below prior to installation.

Application for Interconnection
Preliminary Service Request (PSR) - for Electric Service Panel Inspection

Before solar is built or installed, the Engineering Inspector needs to inspect the eletric meter panel to determine if the panel is complaint to today's standards (i.e. EUSERC rated).

Form 41 - Net Surplus Compensation

Required Plaques

BVES, Inc. requires that the electric service panel, AC disconnect and DC disconnect (when applicable) be labeled with plaques that meet the following requirements:

  • Red, hard plastic and permanently affixed

  • White engraving that is clearly legible

  • Cautionary language

Electric Service Panel Requirements and Example:

  1. Diagram of the structure on which the generation device is located

  2. Language denoting all electric power sources on or in the premises

  3. See example: Service Panel Plaque

AC Disconnect Requirements and Example:

  1. Nominal operating AC voltage

  2. Nominal operating AC frequency

  3. Maximum AC power

  4. Maximum AC current

  5. Maximum overcurrent device rating for AC module protection

  6. See example: AC Disconnect

DC Disconnect Requirements and Example:

  1. Open circuit voltage

  2. Operating voltage

  3. Maximum system voltage

  4. Operating current

  5. Short circuit current

  6. Maximum power

  7. See example: DC Disconnect

*If the above requirements are not met, permission to interconnect may be delayed by BVES, Inc.

Helpful Information

Frequently Asked Questions (FAQs)

About NEM and Net Surplus Compensation (relatively new features of NEM):

Tariff Schedule NEM

The NEM rate described on this schedule explains how NEM works. The otherwise applicable tariff (OAT) doesn’t change but the way the Customer’s bill is calculated will change. Please read Sec. 5a that refers to system sizing and contact BVES, Inc. if you have any questions. The system must be sized primarily to offset part or all of the customer’s own electrical requirements.

Sample Draft of Interconnection Agreement

For customer review only (please do not fill this out)

After BVES, Inc. receives a signed "job card" from the appropriate regulatory authority (city or county, depending on locale), BVES, Inc. performs a final inspection of the new wind or solar system. Once that is complete, BVES, Inc. countersigns and fully executes the Interconnection Agreement. The date BVES, Inc. executes the agreement is the first date of the 12 month "Relevant period." BVES, Inc. fills out the Interconnection Agreement based on the information supplied in the Application for Interconnection.

Rule 21 (applies to interconnection to the BVES, Inc. system)

This is a utility’s formal set of rules for interconnecting to the BVES, Inc. system. Applicable only if you are actually planning to move forward with installing generation.

To receive additional information, please contact the Public Purpose Program Coordinator at 800.808.BVES (2837).

Net Energy Metering (NEM) Program Closure

The Net Energy Metering (NEM) Program has reached its cap and is closed, effective January 1, 2018.

Customers with pending NEM projects must have them approved by BVES, Inc. and interconnected no later than February 15, 2018. Customers who are not interconnected by February 15, 2018 will not be accepted under the current NEM Program.

BVES, Inc. is currently considering options for a long-term alternative to the NEM Program.

In accordance with the California Public Utilities Commission, regulated utilities like BVES, Inc. are required to offer the NEM program until solar energy generated from the program reaches five-percent of its non-coincident peak demand, which occurred in October 2016.

Current NEM Customers

Customers whose solar and/or wind projects are interconnected before the NEM closure will remain on the original NEM tariff for 20 years from the date of their original interconnection to BVES, Inc. After 20 years, they will be eligible for the successor tariff. Eligible customers who apply for solar and/or wind interconnection after the successor tariff is approved will qualify for that tariff.